300693

100MW/200MWh Utility Project

The 200MW/400MWh energy storage power station in Kaiyang County is located in Shuangliu Town, Guiyang City. It is one of the 15 optimally configured independent energy storage demonstration projects within Guizhou Province, and the first centralized energy storage power station in Guiyang City. As a part of Guizhou Province's 2023 independent energy storage demonstration projects, it effectively guarantees a high-quality, safe, reliable, and highly efficient power supply for the local area, while playing a crucial supporting role in building a modern energy system in Guizhou.



Working Around the Clock, Going All Out

The SINEXCEL on-site energy storage team strictly executed their plans with seamless coordination. They completed the preliminary wiring, individual unit commissioning, and overall system commissioning in just 7 days. Within 10 hours, they rapidly achieved everything from the 35kV grid-connection test to full-capacity grid-tied operation, collaborating with the client to deliver the project on schedule, efficiently, and to a high standard.


Black Start Capability, Commissioning-Friendly

The energy storage products are equipped with a complete black start function. Before the site is connected to the grid, a black start can be initiated simply by using the DC power output from the battery system. This allows for back-to-back power testing both on and off the grid, which significantly shortens the commissioning cycle and facilitates rapid grid connection for the project.


Modular Multi-Branch, Stable Operation

Each Power Conversion System (PCS) contains 10 power modules. By utilizing the pioneering modular multi-branch technology, it provides one-to-one charge and discharge management for the 10 battery clusters within a single 3.44MWh battery cabin. In this project, a total of 580 PCS modules independently manage 580 battery clusters. This solves the "weakest link" effect (barrel effect) and circulating current issues, significantly improving overall battery utilization.


Deployment
2023
Location
Guiyang, Guizhou, China
Capacity
100MW/200MWh
Product
29*3450K PCS + 2*1725kW PCS
エネルギーの自由を実現する
シンプルかつ柔軟な仕組みで、安定したエネルギー利用を支えます。
お問い合わせ
  • ご関心のあるソリューション・製品*
  • SINEXCELをどこでお知りになりましたか?*
  • 「プライバシーポリシー」を読み、同意します。

    盛弘が業務上の連絡および社外とのコミュニケーションに使用するメールアドレスは、@sinexcel.com、@sinexcel.cn、@global.sinexcel.com のいずれかで終わるものに限ります。これら以外のドメインを使用するメールアドレスは、盛弘が正式に認めたものではありません。不測の損失を避けるため、送信元のメールアドレスを十分にご確認ください。
  • 名前を入力してください
    閉める
    送信成功
    証券コード
    300693.SZ
    シンエクセル・ジャパン株式会社 〒160-0023 東京都新宿区西新宿7-20-1
    SINEXCELグローバル本社 〒518000 中国広東省深圳市南山区松白路1002号
    brand@sinexcel.com
    400-0055-776-1
    Copyright © 2026 SINEXCEL All Rights Reserved BY: Niegoweb プライバシーポリシー | 重要事項
    0755-8651-1588 sales@sinexcel.com