Fortifying the Grid in Japan's Industrial Heartland
SINEXCEL has successfully completed the installation of its first utility-scale 2MW/8MWh energy storage project in Matsusaka, Japan. This milestone marks a major breakthrough in a market known for its stringent grid requirements, reflecting over five years of localized development and steady growth.
Recently, SINEXCEL successfully completed the installation of a 2MW/8MWh energy storage system in Matsusaka, marking the company's first utility-scale project in the country. Powered by two units of SINEXCEL’s 1375kW PCS, this project serves as a critical flexibility resource for the industrial hub of Ise Bay.

An Island Grid Under Pressure

Japan is a global leader in the energy transition, yet its grid remains exceptionally vulnerable. The 8-hour blackout in Tokyo on January 16, 2026, served as a stark reminder of the system's fragility, exacerbated by aging infrastructure and the historic 50Hz/60Hz grid divide.

The project is located in Matsusaka City, a vital node in the Ise Bay Industrial Zone, connecting the Kansai and Chubu economic circles. This region is home to heavy manufacturing industries where power quality is non-negotiable. A voltage dip of mere milliseconds can disrupt production lines and cause significant financial losses.

The challenge was clear: The local grid needed a robust "shock absorber" to balance supply and demand, but the equipment had to meet Japan's incredibly high barriers for entry.

Matsusaka in Google Map


"In Japan, it's not enough to just store energy. The system must be smart enough to regulate voltage and tough enough to survive a disaster."


Beyond grid stability, the economic incentive for energy storage in Japan has reached a tipping point. With solar power flooding the grid, daytime electricity prices frequently plunge, only to spike dramatically during the evening peak—a phenomenon known as the "Duck Curve." Against this backdrop, the Matsusaka project’s 2MW/8MWh configuration represents the "Golden Standard" for the 2026 Japanese market. This duration is perfectly tailored for "Revenue Stacking." It enables asset owners to buy energy at low prices at noon and discharge during the critical 16:00–18:00 window when capacity is tightest and prices are highest, maximizing daily arbitrage.



The Duck Curve schematic.

Meeting Japan's incredibly high barriers for entry is no small feat. Equipment must survive disasters and regulate voltage with millisecond precision. To meet these rigorous standards, the project developers selected SINEXCEL based on its 5-year track record in the Japanese market.

The core of this system is built around two units of the SINEXCEL 1375kW PCS. Crucially, SINEXCEL holds the prestigious JET Certification (Japan Electrical Safety & Environment Technology Laboratories). This self-certification status proves that the PCS meets the strictest electrical safety and grid-connection standards in Japan. For developers, this means bypassing lengthy individual performance tests, drastically accelerating the grid interconnection process.

This hardware was chosen as the "Intellectual Heart" of the station for three reasons:
- Precision Control: Featuring millisecond-level power response, the PCS efficiently regulates voltage, current, and frequency to counter sudden grid fluctuations.
- Power Quality Management: Beyond bi-directional power flow, the equipment proactively supports grid voltage and provides reactive power compensation, significantly enhancing system stability.
- Safety & Efficiency: Designed for utility-scale applications, the modular design incorporates multi-layer protection mechanisms to ensure lifecycle safety while substantially reducing O&M costs.



A Breakthrough for Grid Stability

The successful installation of the Matsusaka project represents a pivot point for SINEXCEL in Japan.


Moving from 30kW/500kW distributed projects to MW-level utility applications proves that SINEXCEL’s technology has matured to meet the "Gold Standard" of Japanese infrastructure.


Once fully operational, the station will perform "Peak Shaving and Valley Filling," alleviating pressure on the Matsusaka grid during high-demand hours and enabling higher penetration of solar power in the region.



SINEXCEL’s first utility-scale deployment in Matsusaka, Mie Prefecture, ready to support the local grid.

From distributed generation to utility-scale support, SINEXCEL is now firmly rooted in Japan, empowering the nation's transition to a resilient, zero-carbon future.


Location
Matsusaka, Japan
Deployment
2025
Capacity
2MW / 8MWh
Configuration
2 x SINEXCEL 1375kW PCS
Highlight
Frequency Regulation, Peak Shaving, Voltage Support
エネルギーの自由を実現する
シンプルかつ柔軟な仕組みで、安定したエネルギー利用を支えます。
お問い合わせ
  • ご関心のあるソリューション・製品*
  • SINEXCELをどこでお知りになりましたか?*
  • 「プライバシーポリシー」を読み、同意します。

    盛弘が業務上の連絡および社外とのコミュニケーションに使用するメールアドレスは、@sinexcel.com、@sinexcel.cn、@global.sinexcel.com のいずれかで終わるものに限ります。これら以外のドメインを使用するメールアドレスは、盛弘が正式に認めたものではありません。不測の損失を避けるため、送信元のメールアドレスを十分にご確認ください。
  • 名前を入力してください
    閉める
    送信成功
    証券コード
    300693.SZ
    シンエクセル・ジャパン株式会社 〒160-0023 東京都新宿区西新宿7-20-1
    SINEXCELグローバル本社 〒518000 中国広東省深圳市南山区松白路1002号
    brand@sinexcel.com
    400-0055-776-1
    Copyright © 2026 SINEXCEL All Rights Reserved BY: Niegoweb プライバシーポリシー | 重要事項
    0755-8651-1588 sales@sinexcel.com